Hi Experts,
I have below requirement
Traveling Time Daily Allowance
Less than 4 hours 0%
4 to 8 hours 25%
8 to 12 hours 50%
More than 12 hours 100%
I have configured above, first defining Max rate (for 24 hours) then calculation guidelines, then i have scaled hours as per my requirement.
But Result is little bit difference in trip..
For Example:
Trip Start Date 01.07.2011 Time 20:00
Trip End Date 02.07.2011 Time 07:00
Means Trip Duration is about 10 Hours
System is calculating Per diem as per below..
01.07.11 01.07.11 20:00 24:00 0.00 1 0.00
02.07.11 02.07.11 00:00 07:00 250.00 1 250.00
Total Amounts for Meals in 250.00
But i think it shall be 500 because total hours is 8 to 12 hours 50%
Any Idea how to achieve above..