Hello Experts,

I'm maintaining certain downtime in APO resource (single mixed). However, when I maintain the downtime of 3 hrs, the planning book (capacity view) shows only 1 hour reduction in available capacity. My shift is 8 hrs and downtime is within the shift.

At the same time, the resource planning table and DS board shows 5 hrs availability on the day of downtime.

This is confusing, since there is difference in available capacities for SNP and PP/DS planning.

Has anyone observed such issue?