Hi Friends ,

I have a problem need suggestions from you.

We have a PM breakdown order which is having 4 operations.

2 of them are completed and spares has been consumed for them.

Now at the month end still two operations are pending and need to be completed

then CO wants PM to TECO orders.

I am thinking of closing this order and then creating a new order with rest two operations in the next month.

Will it be the right way to do the things or any other standard procedure..

Regards

AM