Hi,

In our plant MRP execute daily at background. Please suggest whether system shows MRP list (Transaction MD05) only for the materials which are considered for MRP execution (Due to MRP relevant change) OR it will consider and display the last MRP list for the material though this material was not considered in todayu2019s MRP execution.

For example: For material ABCD there was MRP list exists on 26/5/2010 but from that date there was no any MRP relevant change, there was no planning file entry today when I am trying to check MRP list in MD05 system is giving message u201CNo MRP list existsu201D. My question is this material is not considered for MRP in todays MRP execution then whether system should show last MRP list (exists on 26/5/2010)? or system should not show MRP list as MRP is not executed for this material today.