Hello Experts,

In one of our project, availability control is not performing. Even though there is no budget for the current fiscal year, system is allowing to post the actuals.

We did the below analysis:

1) checked the Availability control activation type in budget profile and is marked as 1.

2) Tolerance limits are maintained for all the target groups except 09-payroll and the action to be taken is mentioned as 3.

3) Checked Specify Exempt Cost Elements node and found that the affected cost element is not mentioned in the list.

4) Even when the availability control is activated with t code CJBN, system is not throwing any errors while actual posting.

Request you to let me know if any thing else have to be checked.

Thanks,

Best Regards,

Guru