Dear all ,
we are using control key in routing for EXTERNAL PROCESSING.
The third operation is externally processed . (suncontraction ) .
every week monday we are running MRP run , now the requirement is :
is it possible to have a fixed date for that week (Say thursaday) this perticular External operation is scheuled ?
if it is not possible in Std SAP , What is the work around for the same ?
pl guide