Hi all,

I had a meta chain which carries 4 master chains.

now we made change in the order ( before order 1-2-3-4 changed order 1-3-4-2) of the 4 master chains in the Meta chain.

collected the meta chain and transported to test system but the changes are not reflecting in Test system.

could any one please tell, what are all i need to collect to transport the meta chain with new chains.

regards

sandy

Accepted Solutions (1)

Accepted Solutions (1)

former_member360228
Contributor
0 Kudos

Hi,

You only needed to collect the meta chain and not the other one's, if your transport was successfull then simply goto your target system open the chain in change mode and you will see the changes. Simply activate that chain and it'll be perfect.

Regards,

Arminder Singh