Consider subcontracting stock in MRP

Hello experts,

Does anybody know what customizing is necesary for a material to consider the subcontracting stock in MRP??

For that material, in in MRP3 view, I have assigned a checking rule for availavility check that has the flag w/o subcontracting unmarked, but it seems that it is not enought.

Can anybody help me?

Thanks !

Laura

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • avatar image
    Former Member
    May 26, 2011 at 07:07 AM

    Hi,

    Please open the below link.I hope it will help.

    http://www.sap-img.com/materials/sub-contracting-cycle.htm

    Add comment
    10|10000 characters needed characters exceeded

  • May 26, 2011 at 07:25 AM

    Thanks Manish for the link, but what I want is just take into consideration as available stock the stock that is in the subcontractor.

    In example, If I have a material that works with a reorder point of 12 units and I have 2 units in my warehouse and 15 units in the subcontractor, I want the MRP to consider those 15 units as available stock.

    My problem is that with that scenario the MRO is generating a purchase requisition and I do not want MRP to generate it.

    Regards.

    Laura

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 26, 2011 at 07:29 AM

    Please check the settings for requirement calculation in transaction code OPPI

    Add comment
    10|10000 characters needed characters exceeded

  • May 26, 2011 at 07:36 AM

    There is no subcontracting stock in OPPI.

    That transaction is for Stock in transfer, blocked stock and restricted use stock.

    I have seen something about a BADI call MD_SUBCONT_LOGIC, does anybody know how it works?

    Regards.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 26, 2011 at 07:38 AM

    Hi Laura -

    For which transaction in Inventory Management are you setting up this Dynamic Availability Check? Please check if you are doing these assignments under the correct IM transaction in SPRO under the node:

    Materials Management -> Inventory Management and Physical Inventory.

    In the material master you should be setting the appropriate Availability Check, as required by your checking startegy i.e. the combination of Availability Check and Checking Rule combination that you have defined in your 'Definition of Checking Rule' in the above setup of Dynamic Availability Check.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 26, 2011 at 07:41 AM

    Define MRP area in OMIZ with subcontract as vendor MRP area.

    Alos open the below link :

    http://aq33.com/material-management/Articles-002545.html