Credit check without new ATP check

Former Member
0 Kudos

Good morning!

Simple question: is it possible to have a credit check on sales order without having a new ATP check (i.e without returning all confirmed quantities to zero)?

Is terms of business scenario, we intent to let the factory to produce the goods even if the customer has passed its credit limit.

Best Regards!

Adriano Cardoso

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks for the fast reply!

Actually we need to leave all the confirmations alone, while de credit check is performed (whether it blocks or not).

Regards.

former_member131745
Product and Topic Expert
Product and Topic Expert
0 Kudos

You can find out more about this in OSS note 377165:

....

2. You can use requirements to delete confirmed quantities in credit

blocked sales orders. These requirements are defined in transaction

VOFM under the menu path 'Requirements -> Subsequent functions ->

...'. The system asks you for a credit status in the respective user

requirement. If this is set to 'Blocked', the system cancels the

confirmed quantity. You may want the system to behave differently.

If this is the case, you can store a separate requirement which does

not cancel the confirmed quantity. As a result, the sales order item

has a confirmed quantity again and consequently, it updates the open

sales order value although the document is credit blocked.

For NON-MRP materials (materials without requirements planning), the

system does not cancel the confirmed quantity despite a

corresponding condition, as described in Note 393304. For further

information about this, refer to Notes 674112 and 914627.

....

I hope this helps.

Gerard

Shiva_Ram
Active Contributor
0 Kudos

If you want the system not to confirm, then in blocking reasons, untick confirmation against delivery block 01 in t.code OVZ7. If you want the system to uncofirm, but still wants to pass the requirements to planning, then go to SPRO->Sales and distribution ->Basic Functions->Availability check and Transfer of requirements->Maintain requirements for transfer of requirements.(t.coe OVB8) I assume routine 1 or 101 must be assigned here. Remove the routine and test again.