Can I delete old Daily Work Schedules?

In Dev System, if I need to delete the Old DWS, I created new names keeping the old parameters.

Do I require to move it through transport to Quality and Production?

When I delete old DWS and save, it prompts for a transport request.

What should I do?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on May 24, 2011 at 02:49 AM

    Why you want to delete the old DWS ?

    You can delete the old DWS if it is not used.

    Also you need to check if there is any WSR that is associated with these DWSs .( work schedules which is using PWS in which the DWS used) . Before deleting you need to make sure that the deleted DWS is not assigned with any of the current WSR

    Add a comment
    10|10000 characters needed characters exceeded

    • As mentioned by Haji, nothing can be added or changed to a transport once it has been released. You will have to create a new transport for any additional changes required. If the second transport is released before the first one is applied into PRD, just make sure that they are both applied in PRD in the same sequence that they were released (since they affect the same objects).

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.