Overtime planning for the workcenter

174 Views

Hi

one finished product as per routing (10 operations) will be finished in 3 days ,working in only one shift (8hrs) as per shift sequence.

Practically he is giving overtime of 8 hrs and manufacturing the product in 2 days.

Overtime will be decided on daily basis as per requirement.

How to in corporate this in Planning and schedulling.

Regards,

srihari.M