Skip to Content

Is it possible to change task list header work center through transaction CA85

Hi,

Is it possible to change task list header work center through transaction CA85, as when I changed it is only changing task list operations work centers not on header.

Thanks

Yogesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Dec 14, 2016 at 02:00 PM

    Hi,

    No, the header will not be changed.

    Mass changes transactions (CA85, CA85N) are developed for operation changes purposes only.


    -Paul

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 14, 2016 at 02:32 PM

    For information only...

    You can set PID ACC_MODE to "X" to get a different view in CA87. But it still doesn't allow mass-change of the header work centre.

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/c0/04cd584ebb11d189110000e8322f96/content.htm

    Also, CA85N does not seem to work for PM task lists..

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 14, 2016 at 04:27 PM

    Thanks Paul & Peter, Query is resolved.