Display collectively planned orders scheduled date

Dear PP experts.

we created plan in MD61 for 100 materials and MRP carried out with lead time scheduling.

Now we want to check for all the planned orders scheduling dates as per operatiions wise collectively.

where can we see,, , individually we are getting in display planned order

Please suggest

Regards,

srihari.M

Edited by: Srihari.M on May 21, 2011 3:09 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 21, 2011 at 02:28 PM

    Hi,

    There's 3 possible solution.

    1st - Create Customize report with planned order table

    PLAF - planned order table.

    2nd - Goto COOISPI and display all the plan order with the selection that you wish enter the plant code & then execute.

    3rd - MD16 Collective Display of Planned Orders report.

    Thank you.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.