Hi SAP gurus,

I want while capacity leveling (CM21) system should not allow to drop an order on wrong work center.

Suppose i have finished material XXX with three different alternative routing for work center WC1, WC2 & WC3. After planning while capacity leveling (CM21) system should allow to drop order (Planned order/production order) only on that work centers. If i select work center other than that there should be warning massage.

tara

Edited by: tara bhapkar on May 21, 2011 1:08 PM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi all,

we have the same requirment as described in the initial posting.

We also would really appreciate to get any hint if this user exit can be used to fullfill this requirement.

Many thanks in advance.

Kind regards,

Thomas

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please chek with exit CY190001 Capacity Planning: Change order operation .

Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks,

I will check and get back to you.

Tara

Former Member
0 Kudos

Hi Rupesh,

could you please elaborate about that exit, How it will work? How to activate it?