Hi SAP gurus,
I want while capacity leveling (CM21) system should not allow to drop an order on wrong work center.
Suppose i have finished material XXX with three different alternative routing for work center WC1, WC2 & WC3. After planning while capacity leveling (CM21) system should allow to drop order (Planned order/production order) only on that work centers. If i select work center other than that there should be warning massage.
tara