Skip to Content
0
Former Member
May 21, 2011 at 11:08 AM

CM21

22 Views

Hi SAP gurus,

I want while capacity leveling (CM21) system should not allow to drop an order on wrong work center.

Suppose i have finished material XXX with three different alternative routing for work center WC1, WC2 & WC3. After planning while capacity leveling (CM21) system should allow to drop order (Planned order/production order) only on that work centers. If i select work center other than that there should be warning massage.

tara

Edited by: tara bhapkar on May 21, 2011 1:08 PM