PPDS PDS priorities

hi experts,

Is it possible to set ppds pds priorities?

The scenario is as follows.

I have 2 PDS with operations and reources as follows -

PDS - 1 PDS - 2

0010 A 0010 B

0020 C 0020 C

All A,B and C are finitely planned.

The requirement is -

If PDS - 1 is not available (due to resource 'A' cap 100 utilized), system should select PDS - 2 to meet the delivery date. (in PPDS production planning run using heuristics (without quota arrangement) )

As per my knowledge, system will create delayed planned orders with PDS -1

Regards,

Yogesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 23, 2011 at 04:02 AM

    Hi,

    You are right in PPDS there is no way to select automaticaly alternative source of supply considering capacity loading. If you are using SCM 7.0 you can enable interactive sourcing during production planning where during planning system can propose to select between two pds interactively and also gives you information about capacity loading.

    Better way to meet this to model this as alternative resource instead of alternative pds and through detail scheduling heuristic or optimizer required resources can be chosen automaticaly.

    Regards,

    Santosh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 24, 2011 at 07:27 PM

    It is not the aim of a PP-heuristic to achieve a finite planning run.Refer to SAP Note No. 551124 for detailed explanation on this.

    As already suggested using alternative modes is always a better option which allows LC or optimizer to do capacity loading more accurately.

    Rgs

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 29, 2011 at 10:02 PM

    Alternative modes in your Routing/Recipe will solve your issue!

    Transactions CA01/2/3 for routing and C201/2/3 for recipes.

    I would go for the Production Planning (PP) scenario and choose routings.

    Will

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.