Skip to Content

Prepaid RA with Quantity Based Method

I have a scenario in result analysis as follows:

1. The customer pays the full amount at the start of the project (prepaid).

2. Before we incur costs this billed amount has to be deferred.

3. Once we start booking T&M to the project we would recognize the revenue based on a POC method.

4. We want the POC method to be quantity based. e.g. Planned hours divided by actual hours

How do we configure this scenario?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 22, 2011 at 08:48 AM

    Use the standard RA method 03 Cost based POC Method to accrue / defer the revenues (prepaid)

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 23, 2011 at 06:58 AM

    Check this note,

    SAP Note 765748 - Results implementation for hours worked

    Hope its useful.

    Add comment
    10|10000 characters needed characters exceeded