I am facing an issue with reorder point planning storage location MRP , the details are as below
Stock Qty.on 05/13/11 - 4 Nos
Qty Issued on 05/13/11 - 1 No
Reorder Level Qty - 4
Replenishment Qty is - 3
Sloc MRP indicator is -2
MRP Type PD
Lot size -EX
Max Lot Size -0
Min lot Size -0
MRP Run on 05/14/11 Created 2 Purchase requisitions of Qty -3 each
It should create only one proposal for 3 Qty.
What could be the possible reason?