serice pr document type pricing procedure not picking in project system

29 Views

Hi,

we have two different pr document types NB,SER in our client , different pricing procedure to for that document type ,but in project system only one document type is allowed for that pr ,we used user exit COZF0001 and changed the document type NB to SER ,we created ser document type pr , that pr is not picking SER document type pricing procedure it is picking NB document type pricing procedure,i created manually using SER pr it's picking correctly ,if i created project through on that time only it is picking wrong pricing procedure

thanks and regards

Vijju...