Dear All,

At the time of Creation of Pruchase Requisition, the account assignment was "A" & it is picking up the Asset Code at the creation of PR, but beside the PR there is a WBS Element is there. WBS is not updated in PR since the WBS was assigned to Asset. All the PR is working one PR WBS is not updated. What would be the reason.

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

Former Member
0 Kudos

Hi.

1 Need to open field wbs elemete for Acc.ass. A

2. Maintain field in asset master data ANLA-POSNR (investment wbs-element)

3. create G/L acoount from AO90 -aquisition account like cost element(90)