Hi,
under Material Management in SPRO under General Settings for Materials Management
1. Set material block for goods movements Lock Exclusively and (ii) Late lock
2. Set Up Material Block for Invoice Verification
Set Up Material Block for Invoice Verification
(ii) Set Up Material Block for Invoice Verification
(iii) Set Up Material Block for Invoice Verification
Pls tell me which option i should select in which case?
Hi,
Each option have some time advantage on the other one, when the subject material is blocked for other users, preventing them from carrying out any IM postings.
For goods movement process, Exclusive block will hold the item code for longer time than Late block.
It is better to go with the stadard settings of 'Exclusive block' for Goods movement and 'blocked at first read' for invoice verification.
Jeeva.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.