on 05-16-2011 10:07 PM
Dear PP Experts,
I have requirement where my client doesn't want to get new scheduled dates from APO upon confirming production order (partial). If order is originally scheduled on 5/15/11 and when we post confirmation today it changes dates in APO and updates current date as scheduled date in ECC (need original 5/15). Thanks for help.
The change required is on APO side - to disable automatic rescheduling (I guess it is in PP/DS).
You should post this also in the relevant APO forum too.