Retain ECC Production Order dates after Partial/confirmation

27 Views

Dear PP Experts,

I have requirement where my client doesn't want to get new scheduled dates from APO upon confirming production order (partial). If order is originally scheduled on 5/15/11 and when we post confirmation today it changes dates in APO and updates current date as scheduled date in ECC (need original 5/15). Thanks for help.