Hi Gurus,

Could any one explain me how the values in the distribution demand planned KF are calculated..i know these are calculated during the SNP heuristics ..but how

Accepted Solutions (1)

Accepted Solutions (1)

aparna_ranganathan
Active Contributor
0 Kudos

Hi

Lets say branch A pulls from branch B. When you run SNP heuristic @ material - branch B , the SNP engine will identify the source of supply as branch A and hence will create a distribution demand (planned) at branch A and distribution receipt (planned) at branch B. After this when you run deployment , the demand and receipts will become distribution demand (confirmed) and distribution receipt(confirmed) respectively.

Thanks

Aparna

Former Member
0 Kudos

Hi Aparna,

Thanks, from your explanation can branch A be a DC or customer and branch B a plant...pls correct me if iam wrong..

aparna_ranganathan
Active Contributor
0 Kudos

That actually depends on your level of planning. If you are running planning at material - customer level , then yes branch A can be a customer that pulls from branch B. But it is very uncommon to run planning at material - customer level - atleast i have not worked on a scenario that requires planning at that level.

The answer to the other part of your question is yes branch A can also be a plant (or DC) that pulls stock from another plant

Thanks

Aparna

Former Member
0 Kudos

Hi Aparna,

Thanks, you are right, it would be appropriate to use the plant-DC combination. My question is now answered so iam closing this..