Hello Experts,
I have a senario where ihave to map a machine (Excavator) with the following specification in SAP ETM:
1. WORKING HOURS PER SHIFT
2. ACTUAL DIESEL CONSUMPTION PER SHIFT
3. STANDERD DIESEL CONSUMPTION PER HOUR
4. STANDERD DIESEL CONSUMPTION PER SHIFT
5. DIFFERENCE IN DIESEL CONSUMPTION
6. PLANED OUT PUT PER SHIFT
7. ACTUAL OUTPUT ACHIEVED FOR SHIFT
8. DIFFERENCE IN OUTPUT
9. ENGINE OIL CHANGING DATA
10.HYDRALIC OIL CHANGING DATA
11.SPARES USED
What i have done in SAP:
1. Created a euipment by Name : Excavator.
2. Assigned the same to a Plant.
Also i am creating a Perfrmance Based Euipment Document for the Excavator to use it on a Project (Project Name: Construction of Road)
With this i am able to track the actual work hours spent by the excavator on the road project.
Now i am not knowing how to go about to key in or capture the above stated rest of details on equipment.
Can any one throw me some light on how to proceed further.
Regards,
Sudarshan.