on 05-12-2011 3:47 PM
Necesito su colaboracion para poder definir la forma de ingresar los tiempos de transporte entre operaciones en una hoja de ruta especfica, de igual manera que sean tenidos en cuenta en el costeo de la orden.
Gracias.
Luisa,
I do not speak Spanish. However, it appears you are asking about managing the amount of time between operations in a production order routing.
Interoperation time can be entered in the route as 'queue' (before the op) or 'Move' time (after the op). It is also possible to schedule 'setup' time and 'teardown' time, which will add delays, but are usually considered part of the operation itself.
Here is SAP online help in Spanish that may illuminate the matter. Although it is for SAP 4.7, this functionality hasn't changed very much in the past few years, and ECC mostly works the same.
http://help.sap.com/saphelp_470/helpdata/es/8a/a586ca4adc11d189740000e8322d00/frameset.htm
General info about Routings
http://help.sap.com/saphelp_470/helpdata/Es/7e/d411b5455911d189400000e8323c4f/frameset.htm
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.