Predefined Rate contract and Billing

MM Gurus,

Can we create any predefined rate contract. My client have yearly based rate contract with vendor. In this rate contract they have segricated the amount for each activity. for example - change of motor -100 rs, change of pump 200.

Whenever the service contractor done the job they have raises the bill for the activity. Then bill should be verified with the job and it should be accounted.

kindly suggect me how i can capture this activities in plant maintenance also.

Thanks and regards

G.Sathish

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 12, 2011 at 05:06 PM

    Hi,

    Satish you can create service PO based on PR generated out of PM order

    Use item category D and account assignment category K in service PO and maintain these services as either service masters or text items in PO

    You can enter service entry sheet based on activity completed (services rendered) by service provider the rate will be as per PO

    Thanks

    Diwakar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.