Hi Experts,

I am using process orders in our project. When I use the capacity planning to level the capacity through transaction CM21, I can despatch the operation without any issue and the associated phase also is getting despatched.

But if I want to deallocate the despatched operation, Iam not able to do that. System says the message, phase can not be deallocated. But once I despatch I find only one line assigned and not two lines as before despatch.

How to select the operation after despatch and how to deallocate?

Please help

Thanks & Regards

Prathib