Skip to Content
0
Former Member
May 09, 2011 at 09:21 AM

Component Qty Split during Backflush

55 Views

Dear Gurus,

We have a problem with the quantity splitting during backflush.

Ex. Prod Order for FG requires PM 500pcs as per BOM. Current SAP stock is 400pcs only. During backflush (production confirmation CO15), there is a deficit error due to insufficient stock (500 > 400). COGI registers 500pcs.

How can we setup the system that during backflush, 400pcs is successfully consumed while leaving a COGI of 100pcs only (instead of 500pcs)?

Thanks for your help.