non appraisal cost

Sir,

i want to know the cost incurred in quality so i created a work center and activity type assigned and the work cetnr is assigned

to quality plan

Now please tell me how to creat QM order to update in material master

and also pls tell me what are the other setting required to obatain the cost for individula quality inspection

Faisal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 08, 2011 at 02:38 PM

    Hii,

    QM cost means ur cost of poor quality of material, then you can map this into two area ur appraisal & Non conformity cost.

    For appraisal cost,

    1) Create an activity Type - Labour hours

    2) Create a work center and attach the activity type in this

    3) Attach this workcenter in the inspection plan

    4) Create a QM order in QK01,

    5) Put the relevenet datas as inspection type, material, cost center, order type , cost center, profit center

    6) execute and assign the orders to the material

    7) Do the result recording and save,. you wil get a pop for recording the activity type

    For non conformity costs

    1) Create a notification after defect recording

    2) create an order for notification QN01,

    3) Also maintain in config SPRO> QM> Quality Notifications> Notification processing > Define costing Parameter > Account assignment for QM orders> maintain plant, notification type, order type, (cost center if needed)

    3) Record the activities using KB21N