Hi Experts,

My client is facing some problem regarding one internal order he created the PO on 31-03-2011 my financial year is april to march, he created two AUC which relates to this PO, the PO contains two line item now he is trying to add freight related condition type ZFB3 and amount but system is throwing an error like budget is exceeded but he is able to change the net price and remaining amounts for both the line items but system is throwing error only in case of freight, my doubt is if budget is criteria why system is not throwing any error in case of other amount modifications, he created PO auc assignment everything he done in 31st march only now he is trying to add freight charges.

Kindly advise