Hello,
What is the differences between "hey for performance efficiency rate" in "basic data" tab in work center and "capacity utilization" in work center header?
Thank you experts
Hello Amin,
About "Key for performance efficiency rate"
Sometimes formula calculation result is hard to be explained according to standard values and formulas. Then this rate(percentage) should be checked. Formulas are the ones set under Capacity tab and Scheduling tab.
About "Capacity utilization rate"
E.g start time is 8:00 and Finish time is 17:00 with 1 hour break, so general operating time is 8 hours. However, if the machine need 2 hours' maintenance time, which means the actual capacity is only 6 hours, so that the capacity utilization rate should be set as 75%.
Hope it is helpful.
best regards,
Jessica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.