on 05-06-2011 1:57 PM
HI
PO was released and inline for A1 approval i mangae to ask A1 to reject or cance the po and iam unable to unrelase the po using me29n or me28 it says document has already outputted(function not possible)
Thank you
a
Hi,
This is because of the designed of Release strategy configuration.
I hope in Release indicator you might have used 1- Cannot be changed
If your requirement is that even if document out putted & still it allows to change use 6- Changeable, new rel. if new strategy. Or values change/outputted.
This allows changing even after document printed.
Rgs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi guys ,
i have also faced the similar issue recently .
i solved like this .
please use ME28 and select the check box Cancel release . Scope of list given as BEST. then given the PO number . i am able to unrelease the already released PO .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I believe you are receiving the error ME175?
With ME29N you cannot cancel a release strategy once the document has
been printed out. This behaviour constitutes a new design. Regarding
ME28 it has been decided to keep the old behaviour and you can cancel
the release if there is at least one message type which has not been
printed out.
Kind regards,
Lorraine
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.