PO for one material with mutiple delivery options

Hi friends:

issue purchase order qty of 10000 pcs to a vendor for material M1 .

1) we want him to supply to two different plants 5000 qty to plant1 and 5000 plant 2 .

is it possible , if possible could someone what is the sequence of steps i need to do.

Thanks for your time.

Thanks

Sweth

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    author's profile photo
    Former Member
    Posted on May 05, 2011 at 01:03 PM

    When u create 2 line items the plant address of 2 plants will be shown in PO.U can see that in Delivery address tab of PO.Only thing is while printing the PO,The ABAPer should write the logic in such a way that it has to print the plant address below the item so the vendor will know which plant it has to be delivered.

    Add comment
    10|10000 characters needed characters exceeded

  • Posted on May 05, 2011 at 12:53 PM

    Hi Sweth,

    While creating a PO, you can create 2 different line items of same material and can mention 2 different plants in the PO

    hence GR which is item dependant, will be with respect to line item level in PO

    GR for first line item, will be made in plant 1

    GR for second line item will be made in plant 2

    Replicate this scenario in Quality landscape, you may get some hint. let me know if you need any more assistance.

    Raghavan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Have a look at your condition if it is customized as group condition or not.

      Group conditions means whether the system calculates the basis for the scale value from more than one item in the document.