Scheduling for Planned orders

0 Kudos

Hi ,

Please suggest what is the way to do Capacity Requirements check while doing MRP/MPS, as on date we get planned orders for which Scheduling is not done automatically,

One has to go to each planned order

GoTo Edit -


>Scheduling----


>system then generates Scheduing log and does Capacity Requirements for that planned order.

I want this to be done for Planned orders in Mass Run.....What is standard Transaction to do this ?

Accepted Solutions (0)

Answers (1)

Answers (1)

sundaresan_velayudam
Active Contributor
0 Kudos
I want this to be done for Planned orders in Mass Run.....What is standard Transaction to do this ?

run a MRP with scheduling 2 Lead time scheduling and capacity planning

& planning mode as delete and recreate

system will generate automatically the scheduling and capacity planning for the material

before that check the config in OPU5 for plan order

check in detail scheduling

scheduling and capacity reqs check is marked

and adjust scheduling