Scheduling for Planned orders

Hi ,

Please suggest what is the way to do Capacity Requirements check while doing MRP/MPS, as on date we get planned orders for which Scheduling is not done automatically,

One has to go to each planned order

GoTo Edit -


>Scheduling----


>system then generates Scheduing log and does Capacity Requirements for that planned order.

I want this to be done for Planned orders in Mass Run.....What is standard Transaction to do this ?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Posted on May 05, 2011 at 06:57 AM
    I want this to be done for Planned orders in Mass Run.....What is standard Transaction to do this ?

    run a MRP with scheduling 2 Lead time scheduling and capacity planning

    & planning mode as delete and recreate

    system will generate automatically the scheduling and capacity planning for the material

    before that check the config in OPU5 for plan order

    check in detail scheduling

    scheduling and capacity reqs check is marked

    and adjust scheduling