How PurRqs Planned dates in MD04 is calculated compared to PurRqs in APO

327 Views

Dear Experts,

Just want to ask how PurRqs Planned dates in MD04 is calculated compared to Availability /Reqmnts Date in RRP3 in APO.

Below are the examples:

In APO RRP3 we have (PurRqs A) = Start date 6/21/2011, Avail / Reqmts Date 7/01/2011

In R/3 MD04 we have the same (PurRqs A) -> Planned dates = 7/02/2011, Delivery date = 6/22/2011, Release date = 6/21/2011, GR pr time = 9

In APO RRP3 we have (PurRqs B) = Start date 7/22/2011, Avail / Reqmts Date 8/01/2011

In R/3 MD04 we have the same (PurRqs B)= Planned dates = 8/03/2011, Delivery date = 7/23/2011, Release date = 7/22/2011, GR pr time = 9

Thanks in advance,

Marcus