Hi Gurus,

Is there a way we can set up to dunning to include all the invoices from the prior level?. For example if a customer is at level 2 dunning and he has couple of invoices at level 1, can we configure the system to generate only level 2 dunning form with both the invoices that are at level 2 and level 1 included as opposed to sending one letter for each dunning level..

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Posted on May 04, 2011 at 11:41 PM

    Hi Chandra,

    Kindly check the customizing in the company code data for dunning:

    transaction F150 -> Menu 'Environment' -> 'Change configuration'

    -> Menu 'Environment' again -> 'Company code data'.

    Please, unmark the field dunning by dunning level.

    Field documentation:

    Separate dunning notice for each dunning level?

    An entry in this field means that a separate dunning notice is created within an account for every dunning level determined.

    Use

    You establish this independent of company code. In contrast to standard dunning in which all items at all dunnning levels are dunned with one dunning notice and the highest occurring dunning level determines the dunning text, when dunning by dunning level a separate dunning notice is produced per dunning level with a different accompanying text in each case. The customer/vendor can then receive several dunning notices from one dunning run.

    Regards,

    Renan Correa

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on May 05, 2011 at 04:17 AM

    Hi

    Please follow the below mentioned path for Dunning

    Step 1:- Define Dunning Areas TCode:-OB61

    Step 2:- Define Dunning Procedures TCode:-FBMP

    Step 3:-Assign Dunning Procedure in Customer Master TCode:-XD02

    Step 4:- Sale Invoice Postings Tcode:-F-22

    Step 5:-Dunning TCode:-F150

    Regards

    Praveen P C

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on May 05, 2011 at 03:12 PM

    Hi,

    Go to FBMP, Select your Dunning Procedure, remove the Dunning internal 1 and save it..Run the Dunning. check the customer master ,for the Dunning Level, Remove Level 1 if its updated.

    Test by the above Process..

    Thanks

    Goutam