Check without RLT (Replenishment Lead Time) not working as expected

Dear All.

We're seeing a sales order ATP situation for externally procured materials, in wihch RLT is not checked. Or at least we've flagged the checkbox in atp config to not include RLT.

However, RLT is still picking up the planned delivery time and GR time.

And if I blank out the GR time and planned delivery timie, then it just confirms it.

???

It acts like RLT is still being used in the check even though RLT is turned off in the availability control (OVZ9)?

Ideas? Anyone see something like this? Does it only work on internally procured materials?

Many Thanks!!!

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Posted on May 04, 2011 at 09:11 PM

    RLT is turned off in the availability control (OVZ9]

    Make sure, the box is checked in OVZ9 to avoid RLT in the availability check. You can do more analysis, by highlighting the sales order line item, then clicking the display availability button. In the next screen click on scope of check button, which shows the OVZ9 details.

    Did you check other parameters like Route, pick/pack time?

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Shiva.

      Thanks for the reply. The check is on in OVZ9.

      It's solved though, I found some custom code which was the cause of the issue.

      It is working as expected now.

      Thanks again.