I have a Rawmaterial coming from different vendore

Now i want to know wether it is possible to carry out different inspection plan with respective with vendore

if it poissible how we can achive it ,what are the setting required

Fasial

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 04, 2011 at 03:46 PM

    say you have V1 & V2 vendors sending you Material M

    Then

    In QP01>header->material assignment -->group counter ,plant,material & Vendor

    Trick is when you change /add new group counter task list changes

    means

    when you enter V1 with gr Counter 1 means its different task list that can have different MIC's from V2 with gr Counter 2.

    SO you have same gr & different gr counter creating two different set of Inspection plan(& MIC's) under one tree.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.