I have a Rawmaterial coming from different vendore
Now i want to know wether it is possible to carry out different inspection plan with respective with vendore
if it poissible how we can achive it ,what are the setting required
Fasial
say you have V1 & V2 vendors sending you Material M
Then
In QP01>header->material assignment -->group counter ,plant,material & Vendor
Trick is when you change /add new group counter task list changes
means
when you enter V1 with gr Counter 1 means its different task list that can have different MIC's from V2 with gr Counter 2.
SO you have same gr & different gr counter creating two different set of Inspection plan(& MIC's) under one tree.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.