Hi expert

I have active QM Info Record In all the plant.

Now scenario is like that.

If am procuring material for R & D purpose the system should not ask for QM info record and time of migo the material should directly goes to unrestricted.

Regard

Nabil

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    author's profile photo
    Former Member
    Posted on May 04, 2011 at 05:12 PM

    Hi,

    If your R & D centre is a different plant than dont activate the quality for the material for that plant.

    Regards,

    Manish Jain

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Manish

      its not an R & D plant, i will be using same material which has quality activated for R & D purpose.

      For the same i have created a new PO type, if i use the PO type of R & D the system should not ask for QM info record for the said document type.

      Regard

      Nabil

  • author's profile photo
    Former Member
    Posted on May 05, 2011 at 05:53 AM

    Hi,

    You have maintained the QM proc. active and inspection setup in material master so that system will ask the info record and generate the inspection lot.

    It is not controled through PO doc. type.

    You can remove the inspection type from inspection setup and avoid creating inspection lot for the material at plant level but you can not remove the QM proc. it is at client level.

    Regards,

    Manish Jain