Dear, experts:
I work in SRM 7.0 SP09 ,
In my scenairo ,the document flow PR -RFx -Contract (SRM)-Contract (ECC).Sometimes ,the use cant make sure the number of the product .because the number of the product Id has relationship with the price .So the user create the PR with the product description in ECC ,and do the sourcing in SRM .After Rfx ,you user will create contract reference the RFX response .You know ,at this monment ,the number of the product ID is defined .But the user cann't enter the product ID in the contract .
yes ,I guess this maybe the SAP standard .Any body has the suggestions about it ? thanks .
BestRegards !
alex !
Hello Alex
please explain your sympton further to understand
i presumed
1. created a PR for MM material master 20003
2. It venture the cockpit and BUYER created BI and Vendor respond the price
3. BUYER converted your RFx into Contract
4. Now Contract distributed to backend system
5. Now BUYER wanted to change from MM 20003 to 20004
now BUYER can not change the above same
since your contract has been distributed to backend sysem then you can not edit it
what you can do one thing
make 20003 as INACTIVATE
and add another item 20004 and distribute to backend system.
Muthuraman