Hi Friends,

In BOM they will change some components suddenly, when they changed it the earlier component open PRu2019s, open POu2019s has to cancel automatically.

Is it possible in standard sap? please tell me..

venkat

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 04, 2011 at 10:01 AM

    Hi Kumar,

    Changing the BOM will not change the demand situation.

    For that to happen you must run MRP once again for that material with planning mode as 3 - Delete and recreate planning data.

    In case PR is converted to PO/Released then you have to manually override the unwanted demand situation.

    Regards,

    Pavan

    Edited by: Pavanakumar on May 4, 2011 3:32 PM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 04, 2011 at 09:50 AM

    I believe it is possible as long as the order has not been released and you run the MRP again chaging the parameters to "2" (Re-expload BOM and routing)

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.