Hi friends

Suppose planning is done for 6 months in that 3 months production is finished, all of sudden if we want to

a) Increase the planning quantity what we need to do, at that time the opening POu2019s, in process Pou2019s how it will act.

b) Decrease the planning quantity what we need to do, at that time the opening POu2019s, in process Pou2019s how it will act.

venkat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

a) if PO means production orders, then new planned orders will be created, but created PO will remain as the MRP cannot modify or erase then. Eventually you can get some exception messages regarding "schedule in time" or similar.

b) SAP will raise some exception message like "20" , suggesting the planner to delete the order. Again, MRP cannot delete PO.