Planned order dates

Dear Experts,

I am working in strategy 40, my issue is when delivery of sales order is eg. 10.05.2011 after running MRP planned order creates but in the stock requirement list the date next to planned order is displays as 10.05.2011, my inhouse production time is 1day, so if i maintain that, in the planned order it displays start date as 09.05.2011 and finish date as 10.05.2011, but when i am converting that planned order to production order it displays start date and finish date as 10.05.2011. what settings i am missing in this case.

Thanks & Regards,

Karad Devidas

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Posted on May 04, 2011 at 09:28 AM

    Basic dates of the production order are calculated by scheduling (I assume capacity requirements scheduling is not used), the hoursd in the routing is what matters. If you run MRP considering the inhouse production time, basic dates for the planned order are calculated using inhouse production time. This may be the reason of the difference.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Devidas Karad

      Hi,

      As pavan said, it is all correct. When you run MRP with planning mode : 1 (adapt planning data) plan date will be create considering in house production in MRP 2 view. There will be no production schedule in planned order since it is not a lead time scheduling in planning mode.

      When you convert this planned order to production order, system will count production date with you routing master data. Date and time will appear. In you case please check possibility configuration of scheduling parameter (OPU3)

      Regards,

      Arman

  • author's profile photo
    Former Member
    Posted on May 04, 2011 at 09:27 AM

    Hi,

    Have you checked the schedule margin key for the material. Also the duration of all the operations in the routing.

    Regards,

    Jagadeesh.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on May 04, 2011 at 09:55 AM

    Hi Devidas,

    In your case system is behaving properly. I guess you have maintianed 1 day as productin time in MRP 2 view of the material master. Which is considered for basic scheduling.

    When any planned orders are created system does basic scheduling and accordingly the time/date are calculted.

    When any production order is created system always does lead time scheduling / exact scheduling. Which considers the time/s maintained in the routing of the corresponding material, which are exact times of production.

    Please check your routing and base qty maintained which I am sure will not be more than a day after calcualtions.

    ( total produciton time = production qty * time in routing / base qty)

    Also please check production order itself in Dates sub tab.

    You can find basic / scheduled / confirmed dates along with time (start as well finish)

    Regards,

    Pavan