One of my PP user is having following question.

**can you explain why the process orders that I created today have order type ZM01 & not ZM02?**

Ca nyou explain what may be the possible reasons with tcodes as I am working in MM and new to PP module.

Thanks,

Kiran

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Posted on May 03, 2011 at 12:37 PM

    In OPPQ- check the conversion, Planned order to production order and check the process order/ or they maintained the ZM01

    or check in material master are yiu assigned the Production scheduler or production scheduler profile

    If production scheduler is maintained , check the production scheduling profile in CORU

    & check the production scheduling profile in CORY- are you maintained the order type ZM01

    Add comment
    10|10000 characters needed characters exceeded

    • for make to order- if the requirement class have order type in OVZG, then order type will flow from SD

      If the order is not relevant to MTO

      Then that order is created manually in CO01 with order type ZM01

      If the order is created bu CO01 then that order doesn't have assignment Plan order in assignment tab

      Edited by: Sundaresan . E. V on May 4, 2011 4:02 PM

  • author's profile photo
    Former Member
    Posted on May 05, 2011 at 10:03 AM

    thanks