/scripts/ahub.form.attachments.js
0

CKM3N Display Incorrect Cost Components Actual Value

Dec 14, 2016 at 04:25 AM

105

avatar image

Hi Experts,

Need your expertise to advise why in CKM3N cost components "Actual Value" showing value in cost components that not consumed by the material.

For example below, this material does not consumed the 3 cost components highlighted.

FYI, even the lower level material also does not consumed any of the 3 cost components.

Kindly help to share your opinions on this.

Thank you.

Regards,

Izzat

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Ratnakar Venkat Dec 15, 2016 at 02:08 PM
0

Hi Izzat,

Is your hourly labor rate is calculated based on your actual/ plan costs like KSS2/KSS4/KSPI,KSII etc and these cost components are derived from labor rate?

Thanks,

Rau

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Rau,

The hourly labor rate is not calculated based on actual/plan costs.

Thanks.

Regards,

Izzat

0
Skip to Content