on 12-14-2016 1:50 AM
Hi,
I wonder how to set the priority before run AV for many production orders which have the same component material. If cannot set the priority for PO, the AV result cannot be the actual material shortage situation.
For example, I have 2 production orders, material X in PO1 needs 500PCS, material X in PO2 needs 400PCS, and there are 500PCS material X in stock. IF there is no priority for them, the stock of material X for 2 production orders is available. But actually, the shortage is 400PCS, once PO1 costs firstly.