Rescheduling orders in APO when making COR6N in ecc

Hi all

Is there any way that APO doesn't reschedule the order each time you make a confirmation in ECC (COR6N)?

it is a problem when the production is behind the scheduled orders, and we want to keep planning board without automatic reschedules after any COR6N

Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Posted on May 04, 2011 at 12:15 PM

    Hi,

    SAP note 492772 provides info on how to prevent this re-transfer and rescheduling.

    I hope it will help you further.

    Regards,

    Tibor