Apr 29, 2011 at 06:01 AM

PM Order TECHO Prob

21 Views

Hi

We have a following peoblem:

We are using PM order processing to capture maintenace job information and cost, we are currently having a prob once we closed the PM order all unprocessed PR attched to it will be deleted. But we cant keep the PM Order open untill Purchasing cycle completed in the system cos in that case work comletion duration calculation will be wrong.

After closing the PM order is there a way of entering PR /PO, with out re-openning it.

We are facing this prob becase Invoice and goods values are send by supplyer after giving all the neccesary goods for maintainece in that case after finishing the job Purchasing cycle will be execuit.

Please advice

Regards

KK