on 04-27-2011 8:59 AM
Hi
Workiing in SAP 4.7
Looking for a report where I can see independent requirements over time, for several materials, based on a time characteristic such as month/week. So for example I want to see the independent requirements for 10 different materials in a list, with the time characteristic on the horizontal axis.
Is there any such report? I am NOT asking for MD05/MD06/MD61/MD62.
Thanks in advance,
Lars
Edited by: Lars Tornblom on Apr 27, 2011 10:09 AM
Check in MD73
if you are using requirement plan then check based on requirement plan else check based on MRP controller by giving period
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.