DP Macro background job

Hi

One of the DP macro jobs failed now and i would like to repeat it..what is the step by step procedure to repeat a cancelled job by copying the original job.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 26, 2011 at 02:18 PM

    Hi,

    by following the procedure the original (failed) job remains untouched.

    So this is basically the same as copying and scheduling it again. The status of the failed one remains - afterwards you will have 2 jobs in SM37.

    Best regards

    Rico Frenzel

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 26, 2011 at 12:57 PM

    Hi,

    in SM37 you mark the job. Then in the Menu "Job" -> "Repeat scheduling". tyoe in the new start condition. Done.

    Best regards

    Rico Frenzel

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      Thanks, but i would like to copy the original cancelled job and repeat it..so when i copy the same it is automatically scheduled..

      now releasing this scheduled job will do or do i need to perform any other operations for the same