MRP run should exclude intracompany STO

Dec 13, 2016 at 07:14 PM

32

avatar image

We have two Plants, one is manufacturing plant and another is a storage plant

We are putting intra-company STO for transfer of Produced stock between these two plants.

So my question to you is: when I run MRP in manufacturing plant, system should not consider these STO's either from Plant A to B or vice versa so that no planned order should be generated against that STO

Is there a way for this as surely it is not a unique situation only for us?

mm | cbp
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.